On a $2 million subcontract with 10% retainage, $200,000 you’ve already earned can sit in someone else’s bank account until the last punch-list item is signed off. For a trade that finished in month four of an 18-month job, that’s a long wait. Knowing how retainage works, what the law allows and how to book it is the difference between a planned cash gap and a surprise one.
Retainage is a portion of each progress payment, usually 5-10% of the amount billed, that the owner or general contractor withholds until the work is complete, as security that the contractor will finish the job and fix defects. You’ll also hear it called retention or a holdback. It’s earned money, paid late on purpose.
What is retainage in construction?
Retainage in construction is money withheld from each progress payment and held until a defined milestone, normally substantial completion. The contract sets the percentage, the release trigger and any reduction. Retainage protects the payer against unfinished work, defects and unpaid lower-tier claims, and it shifts part of the project’s financing onto the contractor.
Here’s how it plays out. A contractor bills for the work completed in the period. The payer approves the amount, deducts the retainage percentage and pays the rest. The withheld amount builds up on every pay application until the release conditions are met.
Why do owners insist on it? Bargaining power at closeout. Once a contractor has been paid 100%, the incentive to come back for a sticking door or a failed inspection fades fast. Retainage keeps money on the table. It also gives the owner a fund to pay someone else to finish the work if the original contractor walks off the job or goes out of business.
The cost lands on contractors and subcontractors. They’ve already paid for labor, materials and equipment, yet a slice of their margin, sometimes all of it, stays with the payer for months. On a thin-margin trade, 10% retainage can be larger than the profit on the job.

Retainage percentages and legal caps
Most construction contracts set retainage between 5% and 10% of each progress payment. The contract controls, but federal and state law can cap the rate, limit when it applies and set release deadlines. Federal construction contracts cap retainage at 10%, and California now holds most private projects to 5%.
Federal work has the clearest rule. FAR 32.103 sets the ceiling and tells contracting officers not to treat retainage as automatic.
Under Federal Acquisition Regulation (FAR) 32.103, retainage withheld on a federal construction contract must not exceed 10 percent of the approved estimated amount, and the contracting officer should not withhold funds without cause. FAR 32.103 also states that retainage should not be used as a substitute for good contract management.
The companion payment clause, FAR 52.232-5, goes further. If the contractor is making satisfactory progress, the contracting officer authorizes payment in full. Retainage of up to 10% applies only when progress falls short. The Part 32 model deviation text released under the 2025 FAR overhaul keeps the same 10% ceiling, but check your agency’s current deviation before you bid federal work.
State rules are a patchwork. Many states treat public projects and private projects differently, and several have tightened their rules in recent years. California is the most recent large example.
California Senate Bill 61 created Civil Code Section 8811, which caps retention on most private construction contracts entered on or after January 1, 2026, at 5 percent of the contract price. According to Foley & Lardner, the cap cannot be waived by contract and excludes purely residential projects of four stories or fewer that are not mixed-use.
Other states rely on mandatory reductions instead of a hard cap, require the payer to hold retainage in an escrow or interest-bearing account, or let the contractor post a retainage bond in place of cash. Is 10% still standard on private work? In many states, yes, by contract. But standard isn’t the same as allowed, and a clause above a statutory cap can be unenforceable. Read the statute for the project’s state before you sign, not after you bill.
How do you calculate retainage?
You calculate retainage by multiplying the amount billed in each period by the contract’s retainage percentage, then deducting it from the payment. Keep a running balance across pay applications, because reductions, change orders and partial releases all change the amount you’re owed or owe. Acumatica Construction Edition tracks retainage by contract and pay application, so the balance updates as each payment posts.
Retainage withheld = Work completed this period x Retainage %
Net payment = Work completed this period – Retainage withheld
Retainage balance = Retainage withheld to date – Retainage released to date
Many contracts cut retainage once the job is half done. One common version withholds 10% until the project reaches 50% complete, then withholds nothing further, so the balance settles at 5% of the contract value. Another drops the rate from 10% to 5% for the rest of the job. Neither is universal. The contract or the state statute decides.
In this illustrative example, a subcontractor has a $2,000,000 contract with 10% retainage until 50% completion and no further withholding after that point.
| Pay app | Billed this period | Cumulative % complete | Retainage withheld | Net payment | Retainage balance |
| 1 | $500,000 | 25% | $50,000 | $450,000 | $50,000 |
| 2 | $500,000 | 50% | $50,000 | $450,000 | $100,000 |
| 3 | $500,000 | 75% | $0 | $500,000 | $100,000 |
| 4 | $500,000 | 100% | $0 | $500,000 | $100,000 |
Without the 50% reduction, the balance at completion would be $200,000. The reduction halves the cash tied up at the end of the job. Worth negotiating? Almost always.
Change orders need the same treatment. An approved change order adds to the contract value and usually carries the same retainage rate, so a $60,000 change billed before the 50% mark adds $6,000 to the balance. Miss it, and your retainage schedule won’t tie to the pay application.

How does retainage flow between owners, contractors and subcontractors?
Retainage stacks. The owner withholds from the general contractor, the general contractor withholds from each subcontractor, and a construction lender may hold its own retainage on loan disbursements. Each layer is a separate obligation with its own rate and release conditions, which is why one project can carry dozens of retainage balances.
On the owner-GC contract, retainage applies to the full contract amount. On GC-sub contracts, the GC usually mirrors the owner’s rate so it isn’t funding the subs’ retainage out of its own cash. Some states limit this. Under California’s SB 61, a contractor can’t withhold a higher retention percentage from a subcontractor than the owner withholds from the contractor.
Lenders add a third layer, and they don’t do the detailed work for you.
The Wisconsin Housing and Economic Development Authority (WHEDA) construction draw guide states that WHEDA retains a percentage of hard costs, usually 5 percent, until substantial completion, charges no interest on the retained funds, and does not track retainage by subcontractor. WHEDA leaves subcontractor-level retainage tracking to the general contractor.
That last point catches people. The lender tracks one number. The GC tracks one per subcontract, each with its own billings, rate, change orders and release status. Retainage also rides along on every draw the owner submits to the lender, which is where mismatches between the GC’s records and the lender’s records tend to surface.
Here’s the problem most guides skip: the early-finishing trade. Site work, foundations and structural steel are often done in the first third of a project, yet their retainage is usually tied to substantial completion of the whole building. That can mean a year or more of waiting on money for work that was accepted long ago. Contractors on construction payment forums regularly describe disputes over this exact point, including arguments over which completion date starts the clock. If you’re the GC, consider trade-by-trade release language in the subcontract. If you’re the sub, negotiate it before you sign. Can you raise it after mobilization? You can, but you’ll have little bargaining power left.
When is retainage released?
Retainage is usually released in two steps. Most of it is paid at substantial completion, when the project can be used for its intended purpose, minus a holdback for open punch-list items. The rest is paid at final completion, once closeout documents and final lien waivers are in. State prompt-payment laws often set deadlines for each step.
The federal rule is a useful model for private contracts too.
FAR clause 52.232-5, Payments under Fixed-Price Construction Contracts, provides that when work is substantially complete, the contracting officer may keep from previously withheld funds only the amount considered adequate to protect the Government, and shall release all remaining withheld funds to the contractor.
Private jobs follow a similar sequence. The architect or owner certifies substantial completion. The contractor submits a retainage billing, often as a separate pay application. The payer releases retainage less a holdback sized to the open punch list. Once the punch list is closed and the contractor delivers warranties, as-builts, operation manuals and final lien waivers, the remaining balance is paid.
Lien waivers are the usual sticking point. Before releasing final retainage, owners and lenders want proof that every tier has been paid. That means conditional waivers when payment is requested and unconditional waivers once funds clear. One missing waiver from a second-tier supplier can hold up the entire release, so collect waivers on every pay application rather than chasing them all at closeout.
What if the payer won’t release it? Your options depend on the contract and state law: prompt-payment interest, a mechanic’s lien on private work or a payment bond claim on public work. Lien deadlines can run from completion, so don’t wait passively for a check that isn’t coming.

How do you account for retainage receivable and retainage payable?
The contractor records retainage it’s owed as retainage receivable, kept separate from regular accounts receivable. The party withholding it records retainage payable, a liability. A general contractor carries both: a receivable from the owner and a payable to each subcontractor. Under ASC 606, retainage that is still conditional may belong in contract assets instead.
Here are the entries for pay app 1 in the example above, assuming the GC is the payer.
| Subcontractor’s books | General contractor’s books | |
| Debit | Accounts receivable $450,000; Retainage receivable $50,000 | Job cost $500,000 |
| Credit | Contract revenue $500,000 | Accounts payable $450,000; Retainage payable $50,000 |
When retainage is released, the subcontractor moves the balance to accounts receivable or cash, and the GC clears the payable.
GAAP reporting adds a wrinkle. Under legacy guidance, retainage simply sat with contract receivables. ASC 606 asks whether your right to the money is unconditional.
Under ASC 606, a receivable is a right to payment that is unconditional, meaning only the passage of time stands between the contractor and the cash. Retainage that still depends on completing work belongs in the contract asset or contract liability balance, as the FASB staff explained in its April 2025 educational paper on retainage for construction contractors.
The FASB staff paper doesn’t change GAAP, and the answer depends on each contract’s terms. Unconditional retainage stays a receivable, with disclosure of the amount expected to be collected after one year. If you issue GAAP statements to a surety or lender, settle the classification with your auditor before year-end, not during fieldwork.
Where does tracking break down? Usually in a spreadsheet. Rates change at 50% completion, change orders add retainage mid-job, partial releases hit some subs and not others, and the GC’s receivable from the owner drifts away from its payables to subs. When was the last time your retainage schedule tied to the general ledger on the first try? If you run more than a handful of jobs, software that ties retainage to every construction draw removes that monthly reconciliation and gives you an aging report you can trust.
Track retainage without the spreadsheet
Elevate Solutions runs construction and real estate accounting on Acumatica cloud ERP. Retainage is calculated on each pay application, carried by contract and line item, and posted to retainage receivable and payable as part of the billing, not in a side schedule. Rate reductions, change orders and partial releases update the balance automatically, so your retainage aging ties to the general ledger every month. Elevate Solutions was founded by a CPA and has served more than 1,000 real estate firms. Book a demo to see retainage tracked on a live project.